Subject: AVENUE "U" REPUMP STATION IMPROVEMENTS

Recommendation/Motion: It is recommended that the Utility Special  District's Board of Directors accept the staff’s recommendation in selecting Holtz Consulting Engineers Inc., to perform these services under the Continuing Engineering Services Contract between the Utility Special District and Holtz Consulting Engineers Inc. executed July 16, 2018.

Originating Dept UTILITY DISTRICT  Costs NOT TO EXCEED $984,653.99 
User Dept.UTILITY DISTRICT Funding Source
AdvertisedNo Budget Account Number
Date   
Paper   
Affected PartiesNot Required   

Background/Summary: 

One of the pumps at the Utility Special District’s potable water repump station located at Avenue “U” has recently failed and the other pump is very old and likely to fail. As a result of the failure and probable failure of the other pump has seriously compromised the ability to pump water into and out of this potable water ground storage tank.  This repump station is critical in maintaining water quality and water pressure for the western portion of the Utility Special District’s potable water distribution system; and is critical for maintaining adequate water supply during peak consumption and fire protection; and the integrity of the piping for the influent fill line to the potable water ground storage tank has been weakened and there is a likelihood of failure; and this project will improve the integrity and reliability of the potable water distribution system.

 
Fiscal Years
Capital Expenditures
Operating Costs
External Revenues
Program Income (city)
In-kind Match (city) 
Net Fiscal Impact
NO. Additional FTE Positions
(cumulative)

III. Review Comments

A. Finance Department Comments:
This agenda also includes an item for Avenue C repairs to be paid from the same Project 18157. Currently there is $1,150,002 available. This item for Avenue U is being approved at this time as overall funding is available to cover this resolution. Funding for Avenue U will be addressed on a separate resolution.
 
B. Purchasing/Intergovernmental Relations/Grants Comments:
 
C. Department Director Review:
Contract Start Date07/16/2018 
Contract End Date07/15/2021
Renewal Start Date
Renewal End Date
Number of 12 month terms this renewal
Dollar Amount
Contractor Company NameHoltz Consulting Engineers
Contractor Contact
Contractor Address

270 SOUTH CENTRAL BLVD, SUITE 207

JUPITER, FL 33458

Contractor Phone Number
Contractor Email
Type of ContractProfessional services
Describe
ATTACHMENTS:
File NameDescriptionUpload DateType
RESOLUTION_Avenue_U_Emergency_(4)_(3).pdfRESOLUTION4/9/2019Resolution
Ave_U_Repump_Station_Improvements_Proposal.pdfPROPOSAL4/3/2019Backup Material
RFQ_947-18_Holtz_signed_contract_LM.pdfRFQ 947-18 HOLTZ SIGNED CONTRACT4/3/2019Agreement
REVIEWERS:
DepartmentReviewerActionDate
UtilityAnswererApproved4/4/2019 - 9:55 PM
PurchasingAnswererApproved4/5/2019 - 6:48 AM
Financesherman, randyApproved4/8/2019 - 10:55 AM
AttorneyBusby, Lina Approved4/8/2019 - 2:54 PM
City ClerkRobinson, ClaudeneApproved4/8/2019 - 2:59 PM
City ManagerAnswererApproved4/9/2019 - 4:54 PM