| | | | | | | | CITY OF RIVIERA BEACH CITY COUNCIL AGENDA ITEM SUMMARY | | | | | | | |
| | | | | | | | Meeting Date: | 11/1/2017 | Agenda Category: | REGULAR RESOLUTION |
| | | | | | | |
| | | | | | | | Subject: | A resolution of the City Council of the City of Riviera Beach, Palm Beach County, Florida, awarding bid No. 849-17-1 to West Construction Inc. of Lantana, Florida for the construction of Over the Water Marina Fuel Office Building in an amount not to exceed $852,255.00; authorizing the Mayor and City Clerk to execute the contract; authorizing the City Manager to approve change orders up to ten percent (10%); total contract value shall not exceed $937,408.50 without authorization by the City Council; authorizing the Director of Finance and Administrative Services to make payment for same from account numbers 422-0000-575-0-6201 and providing an effective date. |
| | | | | | | |
| | | | | | | | Recommendation/Motion: | Staff recommends that the City Council approve the resolution. |
| | | | | | | |
| | | | | | | | Originating Dept | Public Works | | Costs | $852,255 | User Dept. | Public Works | | Funding Source | Proposal Amount $852,255.00 10% Contingency $85,225.50 TOTAL $937,408.50 Approved Amount $937,408.50 | Advertised | No | | Budget Account Number | Fund 422 Dept. /Division 0000 Org. 575 Object 0
Reporting Category: 6201 | Date | | | | | Paper | | | | | Affected Parties | Not Required | | | |
| | | | | | | |
| | | | | | | | Background/Summary: | The Over the Water Marina Fuel Office Building has been scheduled for construction for fiscal year 2017-18. The project consists of the addition of a fuel office building on piles at the east end of pier “D”. The project was advertised for bids on November 27, 2016. Three bidders submitted bids. The lowest bid was submitted by West Construction, Inc. based in Lantana, Florida. The Purchasing Department has reviewed the bids and recommends award of bid to the lowest bidder, West Construction, Inc. in the amount of $852,255.00. Staff recommends that the City Council award the bid for construction of the Over the Water Marina Fuel Office Building project to West Construction, Inc.
Based on the bid results, staff requests City Council approval of contracting with West Construction, Inc. to provide construction services for the construction of the Over the Water Marina Fuel Office Building. |
| | | | | | | |
| | | | | | | | Fiscal Years | 2018 | 2019 | 2020 | 2021 | 2022 | Capital Expenditures | $852,255 | | | | | Operating Costs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | External Revenues | NA | | | | | Program Income (city) | NA | | | | | In-kind Match (city) | NA | | | | | Net Fiscal Impact | $852,255 | | | | | NO. Additional FTE Positions
(cumulative) | N/A | | | | |
| | | | | | | |
| | | | | | | | A. Finance Department Comments: | | | B. Purchasing/Intergovernmental Relations/Grants Comments: | | | C. Department Director Review: | |
| | | | | | | |
| | | | | | | | Contract Start Date | 12/01/17 | Contract End Date | 06/01/18 | Renewal Start Date | | Renewal End Date | | Number of 12 month terms this renewal | | Dollar Amount | $852,255 | Contractor Company Name | West Construction Inc. | Contractor Contact | Martha Morgan | Contractor Address | 318 South Dixie Highway
Suite 4-5
Lake Worth, FL 33460 | Contractor Phone Number | 561-588-2027 | Contractor Email | | Type of Contract | Construction | Describe | |
| | | | | | | |
REVIEWERS: | Department | Reviewer | Action | Date | Public Works | Bailey, Terrance | Approved | 10/23/2017 - 12:23 PM | Purchasing | Answerer | Approved | 10/23/2017 - 12:25 PM | Finance | sherman, randy | Approved | 10/24/2017 - 1:29 PM | Attorney | Answerer | Approved | 10/24/2017 - 2:25 PM | City Clerk | Answerer | Approved | 10/24/2017 - 2:33 PM | City Manager | Answerer | Approved | 10/24/2017 - 3:03 PM |
|
|