| | | | | | | | CITY OF RIVIERA BEACH CITY COUNCIL AGENDA ITEM SUMMARY | | | | | | | |
| | | | | | | | Meeting Date: | 11/2/2016 | Agenda Category: | REGULAR RESOLUTION |
| | | | | | | |
| | | | | | | | Subject: | A resolution of the City Council of the City of Riviera Beach, Palm Beach County, Florida, awarding bid No. 822-16 to B&B Underground Construction Inc. of West Palm Beach, Florida for the construction of West 6th and West 7th Street between Australian Avenue and the Avenue P Canal in an amount not to exceed $829,417.00; authorizing the Mayor and City Clerk to execute the contract; authorizing the City Manager to approve change orders up to ten percent (10%); authorizing the Director of Finance and Administrative Services to make payment for same from account numbers 461-1127-541-0-6301, 140-1123-543-0-6301, and 413-1430-533-0-6301 and providing an effective date. |
| | | | | | | |
| | | | | | | | Recommendation/Motion: | Staff recommends that the City Council approve the resolution. |
| | | | | | | |
| | | | | | | | Originating Dept | Public Works | | Costs | $829,417.00 | User Dept. | Public Works | | Funding Source | | Advertised | No | | Budget Account Number | Fund 413 Dept/Division 1430 Org. 533 Object 0
Reporting Category: 6301 | Date | | | | | Paper | | | | | Affected Parties | Not Required | | | |
| | | | | | | |
| | | | | | | | Background/Summary: | West 6th and 7th Street, between Australian Avenue and the Avenue P canal, has been scheduled for reconstruction for fiscal year 2015-16. The project consists of demolition of the roadway, installation of exfiltration trench for water quality treatment, construction of new asphalt, curb, gutter and installation of sidewalks. The project was advertised for bids on July 31, 2016. Four bidders submitted bids ranging from $829,417.00 to $1,154,108.78. The lowest bid was submitted by B&B Underground Contractors, Inc. based in West Palm Beach Florida. The Purchasing Department has reviewed the bids and recommends award of bid to the lowest bidder, B&B Underground Contractors, Inc. in the amount of $829,417.00. Staff recommends that the City Council award the bid for reconstruction of West 6th and 7th Street, between Australian Avenue and the Avenue P canal to B&B Underground Contractors, Inc. The project is partially funded by the State of Florida (DEP) in the amount of $500,000.00. The balance of funding will be provided from the City’s share of tax on gasoline and the Utility District, for work related to water and sanitary sewer improvements.
Based on the bid results, staff requests City Council approval of contracting with B&B Underground Contractors, Inc. to provide construction services for the reconstruction of 6th and 7th between Australian Avenue and the Avenue P canal. |
| | | | | | | |
| | | | | | | | Fiscal Years | 2016 | 2017 | 2018 | 2019 | 2020 | Capital Expenditures | $829,417.00 | | | | | Operating Costs | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | External Revenues | | | | | | Program Income (city) | NA | | | | | In-kind Match (city) | NA | | | | | Net Fiscal Impact | $829,417.00 | | | | | NO. Additional FTE Positions
(cumulative) | N/A | | | | |
| | | | | | | |
| | | | | | | | A. Finance Department Comments: | | | B. Purchasing/Intergovernmental Relations/Grants Comments: | | | C. Department Director Review: | |
| | | | | | | |
| | | | | | | | Contract Start Date | 11/21/16 | Contract End Date | 05/21/17 | Renewal Start Date | | Renewal End Date | | Number of 12 month terms this renewal | | Dollar Amount | $829,417.00 | Contractor Company Name | B & B Underground Construction, Inc. | Contractor Contact | Stephen Decker, President | Contractor Address | 4050 Westgate Avenue
Suite #110
West Palm Beach, FL 33409 | Contractor Phone Number | 561-249-0341 | Contractor Email | sdecker@bbuconst.com | Type of Contract | Construction | Describe | |
| | | | | | | |
REVIEWERS: | Department | Reviewer | Action | Date | Finance | Answerer | Approved | 10/26/2016 - 6:50 PM |
|
|